Construction Schedule

Hello again Everyone,

Water main construction has been progressing and it is about time for another update.  The two water main crews have finished up along 15th St, all the way from Ironwood SW on the west end to CR 700 W on the east end.  They have also finished up in the Iron Lake Estates subdivision.  Please check out the updated project map below.


Both water main crews will be finishing up the last of the main in Section 4 over this week and into the following week.  If all goes smoothly the first crew expects to be working in Section 3B by next week.  Then the following week the second crew expects to be working there as well.  They will be busy there through the end of the month. 

After that, one of the crews is planning to spend the first week of December in Harvest View (Section 6). 

Once all of the other water main is done both crews will move to Rolling Meadows (Section 7), where they plan to finish out the year. 

The third crew will continue following behind the other two.  They will be installing water services and doing whatever restoration work the weather will allow. 

Many residents have been and continue to hook up to the system.  All sections that have been completed are now active, with the exception of Iron Lake Estates (Section 8).  Flushing and bacteriological testing in that subdivision should take place within the next two weeks. 