Wednesday, February 19, 2014

Construction Update

Hello again Everyone,

Not too much has changed since my last post.  This is mostly due to the bad weather preventing the construction crews from doing their job.  If the nice weather sticks around (fingers crossed) they should be able to get a lot of work done in the coming weeks though. 

Both water main crews are continuing to progress south on Juniper and Ironwood Streets in the Rolling Meadows subdivision.  Once complete they will just have 21st St and Kapok St to complete in Rolling Meadows, which they will start on immediately. 

NIPSCO has a subcontractor, Infrasource, working on relocating the gas main at Dogwood and 10th St.  They hope to be wrapping their work up in time for the water main crews to jump over there as soon as Rolling Meadows is complete. 

I have attached the map as always, but there haven't been any changes since the last post. 


 
Thank you for checking in and for your support.