Friday, October 19, 2012

What is being done to ensure quality work on the water main?
By David Brunsting and Nick Tremmel
When a community is investing in a large project such as the NORWEJ water main in DeMotte, quality of the workmanship is essential. It is certainly of the utmost importance to Abonmarche Consultants as well. Engineers and inspectors have a few tools at their disposal to ensure the main has been installed without any faults. Those tools come in the form of tests, principally a timed hydrostatic leakage test and a bacteria test. The municipal water main must pass these tests to ensure that it is ready for service prior to allowing the public connect to the main. We at Abonmarche oversee these tests.  The pressure testing portion is outlined in this post.
Leaks in a municipal water main are problematic and can be costly. First, a water leak is essentially money being dumped into the ground. When water is pulled out of the municipal well it costs the system in the form of wear and tear on equipment and energy to run the equipment. Since the processed water leaking into the ground will not go through a water meter the costs of treatment cannot be recouped. Even small leaks can cost municipalities tens of thousands of dollars per year if left unattended. Second, leaks can be destructive to existing infrastructure. Even small leaks can undermine and collapse roads and other structures. Additionally a leak invites the possibility (albeit a slim one) for contamination of the water in the line; whereas a sealed system provides a physical barrier to contaminating bacteria.
If the water main could be installed above ground, inspection for leaks would be very simple. Just fill the main with water under system pressure and look for drips. Obviously, water main cannot be installed above ground and must be buried so the question becomes, how do we ensure the connections are acceptable? The answer is pressure testing indicates any leaks and bacteriological testing indicates any contamination from the installation.
The way it works is rather simple. The main to be tested is filled with water and air is expelled by opening hydrants along the way. Once the pipe is completely filled with water from a clean well and almost all of the air is out then the contractor connects a hydrostatic pump to the main. The hydrostatic pump will bring the pressure of the entire line up to the test pressure which in our case is 100 pounds per square inch. This test pressure is roughly two times the system working pressure of 50 PSI. The pump is turned off and the main is held at test pressure for a period of two hours. Because it is almost impossible to get 100% of the air out of a water main the pressure will begin to lower slightly, as seen in the picture. These minor losses are expected, and they are the result of the remaining air trapped in the main, temperature differences, minute movement of the pipe itself and other very miniscule factors. The minor losses do not necessarily indicate a leak, but we have to be sure. There are specifications that lay out (based on hypothesis and empirical data) which draw a line, so to speak, between acceptable and unacceptable pressure losses. After the two hours have passed and there has been a drop in pressure the contractor has to pump the main back up to 100 PSI. The specifications (in our case American Water Works Association, AWWA, C605) outline an allowable amount of water to be used to return the line being tested to the original pressure. This make up water typically amounts to 1 to 2 gallons depending on the length and diameter of the line being tested. Should they go over the allowable amount the test fails and the contractor is responsible for correcting the issue. It is common for a line to initially fail a pressure test but pass on a subsequent attempt. This is most commonly the result of excess air in the main. Though quite rare, on occasion a leak can be found; the cause of the leak could be any number of things, be it material issues or improper instillation or something else altogether.  


Thursday, October 18, 2012


 Pictures of Progress

Above:  Stock pile of 8" diameter pipe near the intersection of Birch Street and 15th Street.

Left:  Workers from Grimmer Construction bolt together an 8" tee on Birch Street just across from the DeMotte Library.

Below:  One of several hydrants installed on 700w just north of 1350n. 

(Photos by David Brunsting)

Tuesday, October 2, 2012

Progress Update

Hello again,

As you may or may not have noticed, progress on all three parts of the project are moving right along. 

On contract A, the well field and treatment facility, the block work for the building is now complete.  As you drive by on 700W take a look to the east and you can get a good idea of what the facility will look like (without a roof that is). 

On contract B, the water main, they are nearly finished with the second section (see updated map below).  One crew will finish up the connection at the highway (US231/SR10) and Begonia then move to 10th st and Halleck Street.  There they will be working southbound along the east side of Halleck Street (there will not be any lane closures on Halleck Street).  Another crew will continue working in the alley one block east of Halleck Street from 10th Street to 8th Place.  The third crew will be testing water main that has already been installed on Begonia, 10th St, 9th St, 8th Place, and Azalea.  They will also be installing services where tests have passed and finally doing restoration work after the services have been installed.  You may have noticed a crew from the directional drilling subcontractor working along Halleck Street as well.  They will be drilling a few areas where open cut instillation is too difficult.  These drilled lengths of pipe will be around 500 feet long and the regular pipe crews will tie onto them sometime down the road. 
On contract C, the tower, fabrication is complete.  The fabrication crew will be cleaning up today and tomorrow, then they will head out.  The next step will be painting.  The paint crew will be here as soon as they can, possibly late this week to early next week.  They will put up a tent around the tower when they paint to protect both the finish as well as the surrounding area from paint.  The hope is to have the painting complete before winter, but that depends on weather.
 
Hopefully this helps to keep everyone informed.  Thanks, as always, for stopping by.