Monday, August 27, 2012

Project Schedules

 
Hello again,
 
Here is the much anticipated post in which I will address the schedules for the different parts of the contracts.  I'd like to begin by saying all information is estimated and very subject to change.  We intend and hope to stay with the schedules but in construction that unfortunately doesn't always work.
 
Contract A - Well Field and Treatment Facility
The building itself is anticipated to be done in early October.  The treatment equipment is expected to be installed by the end of November. 
 
Contract C - Tower
The tower is expected to be assembled by the end of September.  If the weather cooperates the intent is to have it painted by the end of November.  If this does not work it will have to wait until spring to be painted. 
 
Contracts B and B1 - Water Main
Both water main contracts have be broken up into ten separate sections.  The map below shows the approximate locations and limits of each of these sections.  Each of the sections generally have the same amount of pipe to be installed and as a result are expected to take about the same amount of time, somewhere around 4-6 weeks.  The order in which the sections will be completed is based foremost on being out of the way for other anticipated Town projects.  After that the order is based on the Contractor's judgement and may get switched around.  So long as the weather allows it, work is planned to progress through the winter rather than taking a break. 
Section 1 - For the most part, finished now 
Section 2 - From now until early October
Section 3- Early October to mid November
Section 4 - Mid November to mid December
Section 5 - Mid December to mid January
Section 6 - Mid January to early March
Section 7 - Early March to mid April
Section 8 - Mid April to late May
Section 9 - Late May to late June
Section 10 - Late June to early August
 
I would again like to stress that this schedule is likely to change and is really intended simply to give residents a general idea of when to begin expecting work in their area. 
I would also like to note that the first users should not expect water until Spring of 2013. 
Again, I'd like to thank everyone for their curiosity and taking the time to visit.  My next post should be up very soon and will be a very basic to-do list for users who have signed up for water.  